Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Applicable permits and any necessary environmental clearance completed/received | A: 165. Obtain Environmental Clearance - NEPA, ESA, etc. | 05/31/2019 | 05/31/2019 | |
VWW Installation and Improvements Complete | B: 184. Prosser Dam - Vertical Wetted Wall Installation and Modification to Existing | 05/31/2019 | 05/31/2019 | |
Operation and Maintenance of VWW structures | C: 186. Prosser Dam - Vertical Wetted Wall Operation & Maintenance | 05/31/2019 | 05/31/2019 | |
Trap and Haul Adult Lamprey from Columbia and Willamette River | D: 28. NPT Snake Basin - Adult Lamprey Collection, Transport, Hold and Release | 05/31/2019 | 05/31/2019 | |
Updated facilities for lamprey translocation | E: 61. NPT Snake Basin - Upgrade Lamprey Translocation Infrastructure | 05/31/2019 | 05/31/2019 | |
Create habitat & address limiting factors for lamprey | F: 29. MWC SF McKenzie - Harvest and Placement of Large Wood | 09/30/2018 | 09/30/2018 | |
Effective implementation management and timely contract administration | G: 119. PSMFC - Administer the Contract | 05/31/2019 | 05/31/2019 | |
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces | H: 114. Utilize Regional Implementation Plans for Out-Year Project Prioritization and Selection | 02/28/2019 | 02/28/2019 | |
Completed Annual Report | I: 132. Prosser Dam VWW - Submit Progress Report for the period 06/01/2018 to 5/31/2018 | 05/31/2019 | ||
Completed Annual Report | J: 132. MWC SF McKenzie - Submit Progress Report for the period 6/1/2018 - 12/31/2018 | 05/31/2019 | ||
Completed Annual Report | K: 132. NPT Snake Basin Translocation - Submit Progress Report for the period 6/1/2018 - 12/31/2018 | 05/31/2019 |
Primary Focal Species | Work Statement Elements |
---|---|
Lamprey, Pacific (Entosphenus tridentata) |
|
Lamprey, Western Brook (L. richardsoni) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Obtain Environmental Clearance - NEPA, ESA, etc. | 06/01/2018 | ||||||
B | 184 | Prosser Dam - Vertical Wetted Wall Installation and Modification to Existing | 06/01/2018 | ||||||
C | 186 | Prosser Dam - Vertical Wetted Wall Operation & Maintenance | 06/01/2018 | ||||||
D | 28 | NPT Snake Basin - Adult Lamprey Collection, Transport, Hold and Release | 06/01/2018 | ||||||
E | 61 | NPT Snake Basin - Upgrade Lamprey Translocation Infrastructure | 06/11/2018 | ||||||
F | 29 | MWC SF McKenzie - Harvest and Placement of Large Wood | 05/15/2018 | ||||||
G | 119 | PSMFC - Administer the Contract | 06/01/2018 | ||||||
H | 114 | Utilize Regional Implementation Plans for Out-Year Project Prioritization and Selection | 06/01/2018 | ||||||
I | 132 | Prosser Dam VWW - Submit Progress Report for the period 06/01/2018 to 5/31/2018 | 06/01/2018 | ||||||
J | 132 | MWC SF McKenzie - Submit Progress Report for the period 6/1/2018 - 12/31/2018 | 06/01/2018 | ||||||
K | 132 | NPT Snake Basin Translocation - Submit Progress Report for the period 6/1/2018 - 12/31/2018 | 06/01/2018 | ||||||
L | 185 | Periodic Status Reports for BPA | 06/01/2018 |